They have spudded now what?

The unit is called surfside. Section 123 Block 34 They spudded three wells in December 2022 but we have not heard anything since? Anyway to tell if they hit oil?

Hi Rocketpilot,

The Texas RRC (Railroad commissions) website only shows two units spud. 1 in December 2022, the other in January 2023. There is no completion or production information on the site. Here is the link where I obtained this information.

https://webapps2.rrc.texas.gov/EWA/ewaMain.do

1 Like

RR Commission shows only 2 of these well have been spudded by Callon. API 475-38508 was spud on 12/15/2022 & API 475-38509 was spud on 1/9/2023…No completion reports or production available at this time

1 Like

Maybe I’m not looking at it right but I see 4 surfside wells spud late 2022.

38505 38506 38508 38509

There are directional surveys and everything.

To the original poster : how ever many were drilled, if they don’t hit oil something is very wrong.

1 Like

Thank you very much. Would that be normal not to hear if production started yet?

It would be unusually fast if the wells were spud in Dec and they were already reporting production (i.e. made vols in March).

For 4 wells, I’d say probably frac in 3-4 months from spud. Online probably 5-6 months from spud. Get a DO probably 8-9 months. Get paid 10-11 months from spud (first check would have all the back pay). Anything faster than that is a bonus. IMO.

1 Like