Mitsui Baker 101H Status?

Has anyone heard what problems Mitsui has encountered drilling this well? The rig has been on site since October 3, 2025.

1 Like

My understanding is MEP has one well that has a casing leak that must be remedied before fracturing. Not sure if it is the well you are asking about.

2 Likes

Alan, they went too deep on the first lateral and realized they were not in the β€œzone”. Had to back out seal that lateral and go back in and found the zone they were looking for. I believe lateral was permitted for 8500’ they stopped at 6500’. I was told there was a fault line they did not want to take a chance on of getting into. Reason for stopping at 6500’. Drilling has been complete almost a week. In process of removing equipment and rig now. Possibly frac after fracking is complete of Lipsey wells.

Good info! Thanks for sharing!