Any news on proposed Crow well

Hi, I have an interest in Section 35, Township 19 North, Range 4 West, Logan County, Ok.

When pooling hearings started last June, a landman for Slawson was all over my family trying to set up a lease. We talked on the phone, sent a lot of e-mails back and forth, etc. etc. We have not heard from him since 9/29/13 even though we told him we were ready to sign a lease. Did that well proposal go belly up or what. Don't know where to find any information. Any help that anyone can give would certainly be appreciated.

Thanks,

John R. Westhoff

They pooled it on 8/8/2013

http://imaging.occeweb.com/AP/Orders/occ5028012.pdf

A permit was issued on 9/4/2013 and drilling started the next day. I don't see a completion report yet.

http://imaging.occeweb.com/OG/Well%20Records/1DD17205.pdf

They sold a bit of oil off of it in November so it is complete.

Thanks Rick, it never ceases to amaze me how complete strangers are willing to help someone out. You wouldn't happen to know (or know where I can find out) what kind of production they are either getting or expect to get from this well. Many many thanks. If I can ever help someone I would be glad to, I was brought up that way, but unfortunately I am as dumb as a box of rocks when it comes to mineral rights etc.

Rick Howell said:

They pooled it on 8/8/2013

http://imaging.occeweb.com/AP/Orders/occ5028012.pdf

A permit was issued on 9/4/2013 and drilling started the next day. I don't see a completion report yet.

http://imaging.occeweb.com/OG/Well%20Records/1DD17205.pdf

They sold a bit of oil off of it in November so it is complete.

John,

They sold 972 barrels in November. But we don't know if that is 2 days of production or 30?

The API number is 083-24173-00

Search here for API 08324173. You will see a form 1000, 1001A which is the Permit and Spud report. Look for a 1002A to show up with completion data. They have 30 days to file it, but the OCC may be 30 days behind on approval and filing.

http://imaging.occeweb.com/imaging/OGWellRecords.aspx


Sometimes you can find out from the operator or the OCC, but you end up bugging many people and still may not find out before the report is filed. I don't usually dig that deep until I see that it is 4-5 months late.

Once again Rick, I sincerely thank you. I'll keep an eye on the above link and go from there. In those immortal words of Jed Clampett "I hope they pay me in those new fangled dollars, Million-t Dollars."

Rick Howell said:

John,

They sold 972 barrels in November. But we don't know if that is 2 days of production or 30?

The API number is 083-24173-00

Search here for API 08324173. You will see a form 1000, 1001A which is the Permit and Spud report. Look for a 1002A to show up with completion data. They have 30 days to file it, but the OCC may be 30 days behind on approval and filing.

http://imaging.occeweb.com/imaging/OGWellRecords.aspx


Sometimes you can find out from the operator or the OCC, but you end up bugging many people and still may not find out before the report is filed. I don't usually dig that deep until I see that it is 4-5 months late.