# Application process with the Oklahoma Corporation Commission

**URL:** https://www.mineralrightsforum.com/t/application-process-with-the-oklahoma-corporation-commission/74781
**Category:** Carter County, OK
**Created:** [March 13, 2024, 8:30pm UTC](https://www.mineralrightsforum.com/t/application-process-with-the-oklahoma-corporation-commission/74781 "2024-03-13T20:30:32Z")
**Posts on this page:** 3
**Page:** 1

<div class="post-metadata">

### Author: ![Lou\_Atlanta](https://www.mineralrightsforum.com/user_avatar/www.mineralrightsforum.com/lou_atlanta/32/1430_2.png) [@Lou\_Atlanta](https://www.mineralrightsforum.com/u/Lou_Atlanta)
#### Post date: [March 13, 2024, 8:30pm UTC](https://www.mineralrightsforum.com/t/application-process-with-the-oklahoma-corporation-commission/74781/1 "2024-03-13T20:30:32Z")

</div>

Continuing the discussion from [Just got an offer](https://www.mineralrightsforum.com/t/just-got-an-offer/74649/5):

Can someone explain the complete Application process the oil exploration companies have to file with the Oklahoma Corporation Commission in order to drill an oil & gas well? Or maybe a good website that shows the process. Thanks.

---

<div class="post-metadata">

### Author: ![M\_Barnes](https://www.mineralrightsforum.com/user_avatar/www.mineralrightsforum.com/m_barnes/32/10942_2.png) [@M\_Barnes](https://www.mineralrightsforum.com/u/M_Barnes)
#### Post date: [March 14, 2024, 2:06pm UTC](https://www.mineralrightsforum.com/t/application-process-with-the-oklahoma-corporation-commission/74781/2 "2024-03-14T14:06:56Z")

</div>

In general,

1- the operator will file for a spacing order for the reservoir of interest (if it has not already been done in previous years).

2- file for the type of well-vertical or horizontal

3- file for location exception if the well will be placed in a different location than the statutory location in a spacing unit.

4- file for forced pooling to capture all those mineral owners that cannot be found or have not chosen to lease

5-Then the permit will be filed which gives a time frame in which to drill.

6- If there has already been an initial well and they plan to drill more, then they will file for an increased density order, then more wells and location exceptions.

You may find these documents helpful. [0\_The Pooling Process in Oklahoma.pdf](https://www.mineralrightsforum.com/uploads/short-url/9zY8BIUYui5VZiBESeENNKu8uFp.pdf) (340.4 KB) [0\_Royalty-Owners-Booklet-112020.pdf](https://www.mineralrightsforum.com/uploads/short-url/u2cQAsa8sorE3YGesN1JW8cmkGC.pdf) (6.8 MB)

---

<div class="post-metadata">

### Author: ![system](https://www.mineralrightsforum.com/uploads/db5755/original/3X/6/c/6c7c56608c843272ad6e3662ce9562a5956f173e.png) [@system](https://www.mineralrightsforum.com/u/system)
#### Post date: [June 11, 2024, 8:31pm UTC](https://www.mineralrightsforum.com/t/application-process-with-the-oklahoma-corporation-commission/74781/3 "2024-06-11T20:31:00Z")

</div>

This topic was automatically closed after 90 days. New replies are no longer allowed.